Go to top of page
Close
 
Close
Back
ROS Top

Keefer Crossing MS and Comprehensive HS #3 Updates

Keefer Crossing MS and Comprehensive HS #3 Updates

« Back
Message Menu
by: NewCaneyDotCom Active Indicator LED Icon Site Admin
~ 3 weeks, 7 days ago   Oct 29 2020, 1:53pm 
Keefer Crossing MS and Comprehensive HS #3 Updates
 
Forum Image
 
10.23.2020
Keefer Crossing MS and Comprehensive HS #3 Updates
 
Keefer Crossing Middle School overall construction is 45 percent complete, site paving is 85 percent complete, site utilities are 90 percent complete, and structural steel is 100 percent complete. The masonry - brick veneer is two percent complete, the interior concrete masonry unit is 90 percent complete, the interior wall framing is 75 percent complete, and the rough mechanical, electrical, and plumbing is 65 percent complete. Roofing at the main building is 98 percent complete. Roofing at the field house is 40 percent complete.
 
The site clearing for Comprehensive High School #3 is 98 percent complete. The rough grading is seven percent complete, site storm drainage is 10 percent complete, concrete piers are 70 percent complete, and the underground plumbing at the building is two percent complete.
* Reactions disabled on political threads.
What are your thoughts? Log in or sign up to comment
ROS Top




SPONSORED:
ABC & 123 Learning Center Logo The Village Thrift Shop Logo Kingwood Laundromat Logo Reborn Pool Cleaning and More Logo FullScope Pest Control Logo Scapes Environmental Design, Inc. Logo AV Starfish Logo Houston Dynamo Dash Youth Soccer Club Logo Madd Air-Heating and Cooling  Logo Abstract Jiu Jitsu Logo
Sponsor an Ad »



See more of NewCaney.com by logging in
Your online community neighborhood for New Caney-area residents.
Kosmin Media