Keefer Crossing MS and Comprehensive HS #3 Updates

Keefer Crossing MS and Comprehensive HS #3 Updates

« Back
This discussion has been locked.
Message Menu
by: NewCaneyDotCom Active Indicator LED Icon Site Admin  OP 
~ 6 mos ago   Oct 29, '20 1:53pm  
Keefer Crossing MS and Comprehensive HS #3 Updates
 
Forum Image
 
10.23.2020
Keefer Crossing MS and Comprehensive HS #3 Updates
 
Keefer Crossing Middle School overall construction is 45 percent complete, site paving is 85 percent complete, site utilities are 90 percent complete, and structural steel is 100 percent complete. The masonry - brick veneer is two percent complete, the interior concrete masonry unit is 90 percent complete, the interior wall framing is 75 percent complete, and the rough mechanical, electrical, and plumbing is 65 percent complete. Roofing at the main building is 98 percent complete. Roofing at the field house is 40 percent complete.
 
The site clearing for Comprehensive High School #3 is 98 percent complete. The rough grading is seven percent complete, site storm drainage is 10 percent complete, concrete piers are 70 percent complete, and the underground plumbing at the building is two percent complete.
* Reactions disabled on political threads.
What are your thoughts? Log in or sign up to comment
This discussion has been locked.
« Back to Main Page
Views: 347
ROS Top




SPONSORED:
MECKKA Dance Project Logo Silver Accounting Group LLC Logo Yellow Brick Nursery Logo Texas Best Garage Doors, LLC Logo Alpha Omega Gymnastics and Dance  Logo Gamar Cleaning Logo Pillar Plumbing  Logo Truwin - Windows, Doors & Siding  Logo Warren's Custom Pools Logo TexSIS Realty Team Logo
Sponsor an Ad »



See more of NewCaney.com by logging in
Your online community neighborhood for New Caney-area residents.
Kosmin Media