New Keefer Crossing Middle School and Comprehensive HS #3 Update

New Keefer Crossing Middle School and Comprehensive HS #3 Update

« Back
This discussion has been locked.
Message Menu
by: NewCaneyDotCom Active Indicator LED Icon 4 Site Admin  OP 
~ 3 years, 7 mos ago   Oct 7, '20 12:21pm  
New Keefer Crossing Middle School and Comprehensive HS #3 Updates
 
Loading Image...
 
Updated 9.28.2020
 
Keefer Crossing Middle School site paving is 80 percent complete. The structural steel is 95 percent complete, masonry is 20 percent complete, storm and sewer site utilities are 95 percent complete and the rough mechanical and electrical installation is 18 percent complete.
 
Site clearing for Comprehensive High School #3 is 95 percent complete. Rough grading is 55 percent complete. The foundation pad is 100 percent complete and the general contractor is scheduled to start drilling piers this month.
* Reactions disabled on political threads.
What are your thoughts? Log in or sign up to comment
Replies:
No replies yet. Be the first to respond below!
This discussion has been locked.
« Back to Main Page
Views: 1,612
# Replies: 0

Tay's Sprinkler Service
 
The Bridge at Lake Houston Events Logo Flowers of Kingwood Logo New Caney Insurance Agency Logo Yard Birds, Inc. Logo SkeeterCide Mosquito & Wildlife Logo Warren's Southern Gardens Logo Agape Garage Doors, LLC Logo Truwin - Windows, Doors & Siding  Logo Repipe Solutions, Inc. Logo Rosati's Pizza Logo McNamara Law Office, PLLC Logo Wild Birds Unlimited Logo Trademark Kitchen, Bath, & Remodeling Inc. Logo Primrose School of Kingwood at Oakhurst Logo T & K Electric Logo
Sponsor an ad Sponsor an Ad »