Construction Continues On Track at New Keefer Crossing MS and Comprehensive High School #3
 
Loading Image...
 
Construction continues on track at the new Keefer Crossing Middle School campus and the third comprehensive high school.
 
The site paving at Keefer Crossing Middle School is 50 percent complete. The structural steel installation is 90 percent complete, roof decking installation is 90 percent complete, and masonry installation is at 15 percent. The site utilities installation is at 85 percent. The rough mechanical, electrical, and plumbing installation is at 15 percent.
 
The third comprehensive high school site clearing is 85 percent complete. The rough grading, the process of making a level or slope base, is 45 percent complete. Watch the video below for drone footage of both construction sites. : youtu.be/JCHZ-gsq514
 
Update 7.20.2020:
Land Clearing Begins on Comprehensive HS #3
The site has been cleared and rough grading is at 90 percent completion. The building pad is complete. The general contractor will start installing the concrete piers concurrent with the underground storm and sanitary systems.
 
Update 5.21.2020:
Keefer Crossing Middle School Construction Underway
The NCISD Board of Trustees approved an award of construction contract May 18 for the New Comprehensive High School #3 to Gamma Construction. Construction is scheduled to begin within two to three weeks.
 
Also, construction at Keefer Crossing Middle School is progressing well with overall completion at 22 percent. The parking lot paving is at 75 percent, the building foundation is 65 percent complete, and the structural steel is 18 percent complete.
* Reactions disabled on political threads.
What are your thoughts? Log in or sign up to comment
Replies:
Message Menu
Littledannyg Active Indicator LED Icon  New Member
~ 3 years, 9 mos ago   Sep 3, '20 5:56am  
What's caney lane going to look like in New Caney
* Reactions disabled on political threads.
This discussion has been locked.
« Back to Main Page
Views: 1,942
# Replies: 1

Tay's Sprinkler Service
 
Kingwood Tire and Auto Logo Kingwood Pet Resort Logo Old Humble Distilling Company Logo Decker's Carpet Cleaning Logo New Era Stone Logo AireServ Heating and Air Conditioning Logo Truwin - Windows, Doors & Siding  Logo Three B's On The Green Logo Anytime Pest Elimination  Logo Houston Hyperbaric Oxygen Center Logo The Bridge at Lake Houston Events Logo Primrose School of Kingwood at Oakhurst Logo River Rock Pools Logo Kingwood First Baptist Church MDO Logo Kingwood Mulch & Stone - Supplier / Wholesaler Logo
Sponsor an ad Sponsor an Ad »